Case : Jacket
Case Number : 9619
Date Filed : 08/22/2019

IN THE MATTER OF THE MARYLAND ENERGY STORAGE PILOT PROGRAM.

No. Subject Date
1 The Commission - Order No. 89240 Establishing an Energy Storage Pilot Program. Case No. 9619. PC44. (ML 226537) 08/23/2019
2 Public Utility Law Judge Division - Submission of the PC 44 Energy Storage Working Group. Case No. 9619. (ML 228020) 12/31/2019
3 The Potomac Edison Company - Petition for Participation in Energy Storage Pilot Program. Case No. 9619 (ML 229737) 04/15/2020
4 Baltimore Gas and Electric Company - PHI Holdings - Joint Exelon Utilities Application for Approval of Energy Storage Pilot Projects. Case No. 9619 (ML 229744) 04/15/2020
5 Staff of the Public Service Commission - Entry of Appearance of Michael A. Dean. Case No. 9619 (ML 229931) 04/24/2020
6 The Commission - Notice of Comment Period, Hearing Date and Opportunity to Intervene. Case No. 9619 (ML 229950) 04/27/2020
7 Office of People's Counsel - Entry of Appearance for William F. Fields, Deputy People's Counsel, Joseph G. Cleaver, Senior Assistant People's Counsel and Frederick H. Hoover, Assistant People's Counsel. Case No. 9619 (ML 229955) 04/27/2020
8 Maryland Energy Administration - Petition to Intervene. Case No. 9619 (ML 230164) 05/08/2020
9 Prince George's County, Maryland - Petition to Intervene. Case No. 9619 (ML 230172) 05/08/2020
10 DNR/PPRP - Petition to Intervene. Case No. 9619 (ML 230175) 05/08/2020
11 Senator Brian J. Feldman - Comments. Case No. 9619 (ML 230351) 05/21/2020
12 The Commission - Grant of Petitions to Intervene. Case No. 9619 (ML 230427) 05/27/2020
13 Potomac Electric Power Company - Delmarva Power & Light Company - Errata. Case No. 9619 (ML 230481) 05/29/2020
14 MD. League of Conservation Voters - its Letter of Support for BGE Energy Storage Proposal. Case No. 9619 (ML 230549) 06/02/2020
15 University of Maryland Medical Center - Comments. Case No. 9619 (ML 230648) 06/10/2020
16 Baltimore Gas and Electric Company - Delmarva Power & Light Company - Errata to the Application of the Joint Exelon Utilities for Approval of Energy Storage Pilot Project. Case No. 9619 (ML 230781) 06/17/2020
17 The Maryland General Assembly - Comments. Case No. 9619 (ML 230801) 06/18/2020
18 MDVSEIA - Comments. Case No. 9619 (ML 230802) 06/19/2020
19 University of Maryland - Comments. Case No. 9619 (ML 230808) 06/19/2020
20 Maryland Clean Energy Center - Comments. Case No. 9619 (ML 230809) 06/19/2020
21 Energy Storage Association - Comments - Case No. 9619 (ML 230812) 06/19/2020
22 DNR/PPRP - Comments. Case No. 9619 (ML 230814) 06/19/2020
23 Maryland Energy Administration - Comments. Case No. 9619 (ML 230815) 06/19/2020
24 Office of People's Counsel - Comments. Case No. 9619 (ML 230823) 06/19/2020
25 Staff of the Public Service Commission - Comments - (Public Version)  Case No. 9619 (ML 230825) 06/19/2020
26 Future of Energy Initiative - Comments. Case No. 9619 (ML 230827) 06/22/2020
27 Office of People's Counsel - Errata Case No. 9619 (ML 230837) 06/23/2020
28 The Commission - Supplemental Notice of Virtual Legislative-Style Hearing. Case No. 9619 (ML 230922) 06/29/2020
29 Potomac Electric Power Company - Delmarva Power & Light Company - Errata. Case No. 9619 (ML 230981) 07/02/2020
30 The Potomac Edison Company - Amended Petition for Participation in Energy Storage Pilot Program. Case No. 9619 (ML 231036) 07/07/2020
31 Office of Staff Counsel - Errata - Comments on the Applications Submitted for the Maryland Energy Storage Pilot Program.Case No. 9619 (Public and Confidential) (ML 231084) 07/10/2020
32 Staff of the Public Service Commission - Staff Presentation from the July 13, 2020 Hearing  Energy Storage Pilot  Case No. 9619 (ML 231187) 07/17/2020
33 DNR/PPRP - Correspondence. Case No. 9619 (ML 231189) 07/17/2020
34 Delmarva Power & Light Company - Data Response. Case No. 9619 (ML 231215) 07/21/2020
35 Baltimore Gas and Electric Company - Potomac Electric Power Company - Supplemental Information Case No. 9619 (ML 231292) 07/29/2020
36 CRC Salomon, Inc. - Stenographers Record Hearing Date: July 13, 2020. (All Participants Appearing Remotely). Case No. 9619 (ML 231305) 07/30/2020
37 DNR/PPRP - Additional information. Case No. 9619 (ML 231310) 07/30/2020
38 The Potomac Edison Company - Comments. Case No. 9619 (ML 231846) 09/15/2020
39 The Commission - Order No. 89664 on Energy Storage Pilot Proposal. Case No. 9619 (ML 232509) 11/06/2020
40 The Commission - ERRATA. Order No. 89664 Energy Storage Pilot Proposal Order. Case No. 9619 (ML 232573) 11/09/2020
41 - Service list. Case No. 9619. (ML 232604) 11/16/2020
42 The Potomac Edison Company - Request for Expedited Ruling. Case No. 9619 (ML 233059) 12/22/2020
43 ICF - Request to be added to Service Lists. Case No. 9619 ande PC44 (ML 233585) 02/01/2021
44 Baltimore Gas and Electric Company - PHI - Energy Storage Compliance Filing. Case No. 9619 (ML 233601) 02/01/2021
45 The Potomac Edison Company - Petition for Revised Second Project in the Energy Storage Pilot Program. Case No. 9619 (ML 233685) 02/05/2021
46 The Commission - Notice of Virtual Hearing. Case No. 9619 (ML 233972) 03/01/2021
47 Staff of the Public Service Commission - Comments. Case No. 9619 (ML 234272) 03/19/2021
48 Office of People's Counsel - Comments. Case No. 9619 (ML 234273) 03/19/2021
49 The Commission - Order No. 89783 on Town Hill Energy Storage Pilot Proposal of Potomac Edison. Case No. 9619 (ML 234407) 03/30/2021
50 Public Utility Law Judge Division - Submission of the PC 44 Energy Storage Working Group - Case No. 9619 and PC44. (ML 234481) 03/31/2021
51 The Commission - Opportunity to Comment on Energy Storage Report. Case Nos. 9619 and PC44 (ML 234640) 04/02/2021
52 CRC Salomon, Inc. - Stenographers Record Hearing Date. Public Hearing. March 24, 2021. 10:30 a.m. (All Participants Appearing Remotely). Case No. 9619 (ML 234772) 04/14/2021
53 The Commission - Order No. 89805 on Energy Storage Pilot Proposals of Potomac Edison. Case No. 9619 (ML 234898) 04/21/2021
54 Institute for Policy Integrity at NYU School of Law - Comments. Case No. 9619 and PC44 (ML 235214) 05/11/2021
55 Staff of the Public Service Commission - Comments - Regarding the Energy Storage Working Group Report - Maryland Energy Storage Pilot Program  Case No. 9619 and PC44. (ML 235245) 05/12/2021
56 The Potomac Edison Company - Energy Storage Compliance Filing. Case No. 9619 (ML 236357) 07/30/2021
57 The Potomac Edison Company - Energy Storage Compliance Filing. Case No. 9619 (Confidential) (ML 236358) 07/30/2021
58 Potomac Electric Power Company - Baltimore Gas and Electric Company - its Updated Storage Project Costs and Operational Dates. Case No. 9619 (ML 237251) 10/01/2021
59 Office of People's Counsel - Comments Regarding the Joint Exelon Utilities’ Updated Storage Project Costs and Operational Dates Filing. Case No. 9619 (ML 238156) 12/13/2021
60 The Commission - Letter Order Approving Operational Date Extensions. Case No. 9619. (ML 238195) 12/15/2021
61 The Potomac Edison Company - its Request for Extension of Operational Deadline. Case No. 9619 (ML 238389) 12/30/2021
62 The Potomac Edison Company - its Request for Extension of Operational Deadline for Town Hill Project. Case No. 9619 (ML 238406) 01/03/2022
63 Office of People's Counsel - Entry of Appearance. Case No. 9619 (ML 238432) 01/04/2022
64 Delmarva Power & Light Company - its Request for Extension of Operational Deadline of the Elk Neck Battery Storage Project to July 31, 2022. Case No. 9619 (ML 238618) 01/18/2022
65 Office of People's Counsel - Comments. Case No. 9619 (ML 238691) 01/24/2022
66 The Commission - Letter Order to The Potomac Edison Company approving operational date extension. Case No. 9619. (ML 238743) 01/26/2022
67 The Commission - Letter Order to The Potomac Edison Company approving operational date extension. Case No. 9619. (ML 239017) 02/09/2022
68 Office of People's Counsel - Comments - Energy Storage Project Deadline. Case No. 9619 (ML 239251) 02/18/2022
69 The Commission - Letter Order to DP&L approving Operational Deadline Extension. Case No. 9619. (ML 239305) 02/23/2022
70 The Potomac Edison Company - its Requests to change the Urbana Pilot Battery Storage Location, Extend the Operation Date and Increase the Project's Capital Budget. Case No 9619 (ML 240620) 05/09/2022
71 Office of People's Counsel - Entry of Appearance. Case No. 9619 (ML 241012) 06/09/2022
72 The Commission - Service list. Case No. 9619. (ML 241030) 06/10/2022
73 Office of People's Counsel - its Comments on Potomac Edison Company's Requests to Change the Urbana Pilot Battery Storage Location, Extend Deadlines and Increase the Capital Budget. Case No. 9619 (ML 241070) 06/13/2022
74 The Potomac Edison Company - Entry of Appearance. Case No. 9619 (ML 241086) 06/14/2022
75 The Commission - Letter Order to The Potomac Edison Company approving a project alteration for its Urbana energy storage pilot project. Case No. 9619. (ML 241110) 06/15/2022
76 The Commission - Service list. Case No. 9619. (ML 241186) 06/22/2022
77 Potomac Electric Power Company - its request for approval of a revised project's operational date for the National Harbor storage pilot project. Case No. 9619 (ML 241693) 07/29/2022
78 Southern Maryland Electric Cooperative, Inc. - its Request for Approval of a Battery Storage Pilot Program. Case No. 9619 (ML 242045) 08/25/2022
79 Office of People's Counsel - its Response to Potomac Electric Power Company's Request for Approval of a Revised Project Operational Deadline. Case No 9619 (ML 242075) 08/29/2022
80 Council Member Edward Burroughs III - Comments regarding the location of Pepco's Lithium Battery Sorage Unit. Case No. 9619 (ML 242104) 08/30/2022
81 The Commission - Letter Order to DP&L accepting tariff revisions. Case No. 9619. (ML 242134) 08/31/2022
82 The Commission - Service list. Case No. 9619. (ML 242239) 09/08/2022
83 The Potomac Edison Company - its request for a second extension to the operational deadline for the Town Hill Project, and approval of an update to the contract price. Case No. 9619 (ML 242248) 09/09/2022
84 Baltimore Gas and Electric Company - its Request for Extension of the Operational Deadlines of the Chesapeake and Fairhaven Energy Storage Projects. Case No. 9619 (ML 242463) 09/27/2022
85 Solar Energy Industries Association - Comments on SMECO'S Request for Approval of a Battery Storage Pilot Program. Case No. 9619 (ML 242497) 09/29/2022
86 The Commission - Letter Order to SMECO approving Energy Storage Pilot Program. Case No. 9619. (ML 242815) 10/26/2022
87 The Commission - Letter Order to BGE approving operational deadline extension. Case No. 9619. (ML 300078) 11/09/2022
88 The Commission - Order No. 90453 Order Directing Status Updates On Energy Storage Pilot Projects. Case No. 9619 (ML 300635) 12/27/2022
89 The Commission - Order No. 90454 Order on Report of Energy Storage Working Group. Case No. 9619 (ML 300637) 12/27/2022
90 The Potomac Edison Company - Project Status Update. Case No. 9619 (ML 301003) 01/25/2023
91 Potomac Electric Power Company and Delmarva Power & Light Company - Status Report on Energy Storage Projects. Case No. 9619 (ML 301039) 01/26/2023
92 Baltimore Gas and Electric Company - Status Report on Energy Storage Projects. Case No. 9619 (ML 301043) 01/26/2023
93 Potomac Electric Power Company - its Request for a revised project operational date for the National Harbor/Livingston Road battery energy storage system project located at Pepco’s Livingston Road Substation in Prince George’s County. Case No. 9619 (ML 301319) 02/14/2023
94 Baltimore Gas and Electric Company, Potomac Electric Power Company and Delmarva Power & Light Company - Request for Extension of Time to File 2023 Metrics Report. Case No. 9619 (ML 301379) 02/16/2023
95 Office of People's Counsel - Withdrawal and Entry of Appearance. Case No. 9619 (ML 301475) 02/23/2023
96 The Commission - Service list. Case No. 9619. (ML 301481) 02/23/2023
97 The Commission - Grant of Request for Extension. Case No. 9619 (ML 301747) 03/13/2023
98 Office of People's Counsel - its Comments on Potomac Electric Power Company’s Request for Approval of a Revised Project Operational Date. Case No. 9619 (ML 301882) 03/20/2023
99 The Commission - Letter Order to Pepco approving extension of operational deadline. Case No. 9619 (ML 301933) 03/22/2023
100 Indian Head Highway Area Action Council - Request to be added to the Service List. Case No. 9619 (ML 302324) 04/10/2023
101 Indian Head Highway Area Action Council - Comments. Case No. 9619 (ML 302353) 04/11/2023
102 The Commission - Service List. Case No. 9619. (ML 302359) 04/12/2023
103 Baltimore Gas and Electric Company - its Further Request for Extension of the Operational Deadline of the Fairhaven Energy Storage Project. Case No. 9619 (ML 302460) 04/18/2023
104 The Potomac Edison Company - Update to Service List. Case No. 9619 (ML 302868) 05/11/2023
105 The Commission - Service List. Case No. 9619. (ML 302869) 05/11/2023
106 The Potomac Edison Company - Annual Report for 2022. Case No. 9619 (ML 302899) 05/12/2023
107 IHHAAC, Inc. - Comments. Case Number 9619 (ML 302913) 05/13/2023
108 Potomac Electric Power Company - 2023 Energy Storage Projects Metrics Report. Case No. 9619 (ML 302936) 05/15/2023
109 Baltimore Gas and Electric Company - 2023 Energy Storage Projects Metrics Report. Case No. 9619 (ML 302942) 05/15/2023
110 Office of People's Counsel - Comments on the Baltimore Gas and Electric Company’s further request for extension of the operational deadline of the Fairhaven Energy Storage Project. Case No. 9619 (ML 303084) 05/22/2023
111 The Commission - Letter Order to BGE approving revised operational start date. Case No. 9619. (ML 303235) 05/31/2023
112 IHHAAC, Inc. - Comments. Case No. 9619 (ML 303432) 06/09/2023
113 Baltimore Gas and Electric Company, Potomac Electric Power Company, and Delmarva Power & Light Company - Energy Storage Pilot Act Report. Case No. 9619 (ML 303763) 06/28/2023
114 The Commission - Service List. Case No. 9619. (ML 303964) 07/07/2023
115 Office of People's Counsel - Entry of Appearance. Case No. 9619 (ML 303959) 07/07/2023
116 Staff of the Public Service Commission - Comments Regarding the Maryland Energy Storage Pilot Program Utility Data Reports. Case No. 9619 (ML 304145) 07/18/2023
117 Potomac Electric Power Company - Status Report on Energy Storage Projects. Case No. 9619 (ML 304245) 07/25/2023
118 The Potomac Edison Company - Status Report on Energy Storage Projects. Case No. 9619 (ML 304252) 07/25/2023
119 Baltimore Gas and Electric Company - Status Report on Energy Storage Projects. Case No. 9619 (ML 304254) 07/25/2023
120 Southern Maryland Electric Cooperative, Inc. - Status Report on Energy Storage Projects. Case No. 9619 (ML 304291) 07/26/2023
121 Potomac Electric Power Company - Comments and Request to Amend Order No. 89664. Case No. 9619 (ML 304951) 09/11/2023
122 Councilmember Edward Burroughs III - Comments on PEPCO’s proposed move of battery storage location from Livingston Rd in Oxon Hill. Case No. 9619 (ML 304995) 09/13/2023
123 Indian Head Highway Area Action Council, Inc. - Comments. Case No. 9619 (ML 305125) 09/18/2023
124 The Commission - Notice of Comment Period. Case No. 9619 (ML 305140) 09/19/2023
125 Delmarva Power & Light Company - its Request for the Operational Deadline for the Ocean City battery energy storage system project located at 112 100th Street, Ocean City, MD. Case No. 9619 (ML 305183) 09/21/2023
126 Baltimore Gas and Electric Company, Delmarva Power & Light Company and Potomac Electric Power Company - Comments. Case No. 9619 (ML 305628) 10/16/2023
127 The Potomac Edison Company - Comments. Case No. 9619 (ML 305641) 10/16/2023
128 Potomac Electric Power Company - Proposal of the Fairmount Heights Microgrid Project. Case No. 9619 (ML 305668) 10/17/2023
129 The Potomac Edison Company - Service List Update. Case No. 9619 (ML 305940) 11/01/2023
130 The Commission - Service List. Case No. 9619. (ML 305955) 11/02/2023
131 Baltimore Gas and Electric Company - Notice of Operational Status of the Fairhaven Energy Storage Project. Case No. 9619 (ML 306070) 11/13/2023
132 Office of People's Counsel - OPC Comments on the PEPCO's Request to Amend Order No. 89664. Case No. 9619 (ML 306240) 11/20/2023
133 Office of People's Counsel - Comments on OPC Comments on Delmarva Power & Light Company’s further request for extension of the operational deadline of the Ocean City battery energy storage system project. Case No. 9619 (ML 306337) 11/28/2023
134 Delmarva Power & Light Company - its Request a One Year Extension of its Operational Deadline for the Ocean City battery energy storage system project located at 112 100th Street, Ocean City, MD. Case No. 9619 (Confidential) (ML 306986) 01/05/2024
135 Delmarva Power & Light Company - its Request a One Year Extension of its Operational Deadline for the Ocean City battery energy storage system project located at 112 100th Street, Ocean City, MD. Case No. 9619 (Public Version) (ML 306987) 01/05/2024
136 The Potomac Edison Company - Further Extension of the Operational Deadline of the Town Hill Energy Storage Project. Case No. 9619 (ML 307038) 01/10/2024
137 Potomac Electric Power Company - its Further Request to Amend Order No. 89664. Case No. 9619 (ML 307102) 01/16/2024
138 Potomac Electric Power Company - its Further Request to Amend Order No. 89664. Case No. 9619 (Confidential) (ML 307103) 01/16/2024
139 The Potomac Edison Company - its Supplement to the Petition for a Further Extension of the Operational Deadline of the Town Hill Energy Storage Project. Case No. 9619 (ML 307180) 01/18/2024
140 The Potomac Edison Company - Status Report on Energy Storage Projects. Case No. 9619 (ML 307217) 01/22/2024
141 Potomac Electric Power Company’s and Delmarva Power & Light Company - Status Report on Energy Storage Projects. Case No. 9619 (ML 307221) 01/22/2024
142 Office of People's Counsel - Supplemental Comments on Delmarva Power & Light Company’s Further Request for Extension of the Operational Deadline. Case No. 9619 (ML 307465) 02/02/2024
143 The Commission - Letter Order to DP&L approving for operational deadline extension. Case No. 9619. (ML 307508) 02/07/2024
144 Office of People's Counsel - Supplemental Comments on PEPCO's Comments and Request to Amend Order No. 307579. Case No. 9619 (ML 307580) 02/12/2024
145 The Commission - Letter Order to PEPCO accepting filing. Case No. 9619. (ML 307607) 02/14/2024
146 The Commission - Order No. 91039 on Energy Storage Pilot Reporting. Case No. 9619 (ML 307861) 02/27/2024
147 Office of People's Counsel - Withdrawal of Appearance. Case No. 9619 (ML 308006) 03/05/2024
148 The Commission - Service List. Case No. 9619. (ML 308012) 03/05/2024
149 The Potomac Edison Company - its Request for Further Extension of the Operational Deadline for the Town Hill Energy Storage Project Case No. 9619 (ML 308146) 03/08/2024
150 Office of People's Counsel - Comments on Potomac Edison Company’s Request for Further Extension of the Operational Deadline for the Town Hill Energy Storage Project. Case No. 9619 (ML 308677) 04/01/2024
151 The Commission - Letter Order to The Potomac Edison Company approving request to toll operational deadline of its Town Hill Pilot Project. Case No. 9619. (ML 308756) 04/03/2024
152 The Commission - Order No. 91088. PC44 and Case No. 9619 (ML 308811) 04/05/2024
153 Office of People's Counsel - Withdrawal and Entry of Appearance. Case No. 9619 (ML 308918) 04/12/2024
154 The Commission - Service List. Case No. 9619. (ML 308934) 04/15/2024
155 Potomac Electric Power Company - 2024 Energy Storage Projects Metrics Report. Case No. 9619 (ML 309403) 05/01/2024
156 The Potomac Edison Company - Learnings on the Development of Battery Energy Storage Systems Report. Case No. 9619 (ML 309420) 05/01/2024
157 Baltimore Gas and Electric Company - 2024 Energy Storage Projects Metrics Report. Case No. 9619 (ML 309423) 05/01/2024
158 The Potomac Edison Company - its Further Extension of Operational Deadline of the Maryland Energy Storage Pilot Program of the Town Hill Energy Project. Case No. 9619 (ML 309988) 05/31/2024
159 Office of People's Counsel - Comments on the PEPCO’s proposal for the Fairmont Heights Microgrid Project to fulfill the Maryland Energy Storage Pilot Program Act. Case No. 9619 (ML 310177) 06/10/2024
160 The Commission - Letter Order to Pepco granting request regarding Fairmont Heights Microgrid Pilot project. Case No. 9619. (ML 310240) 06/13/2024
161 Office of Staff Counsel - Draft Energy Storage Pilot Program Interim Report. Case No. 9619 (ML 310279) 06/14/2024
162 Baltimore Gas and Electric Company - Errata to 2024 Energy Storage Projects Metrics Report. Case No. 9619 (ML 310398) 06/24/2024
163 The Commission - Letter Order to The Potomac Edison Company Approving Operational Deadline Extension. Case No. 9619. (ML 310903) 07/17/2024
164 Potomac Electric Power Company and Delmarva Power & Light Co. of MD - Status Report on Energy Storage Projects. Case No. 9619 (ML 310988) 07/19/2024
165 Choptank Electric Cooperative, Inc. - Withdrawal and Entry of Appearance. Case No. 9619 (ML 311360) 08/01/2024
166 The Commission - Service List. Case No. 9619. (ML 311367) 08/01/2024
167 Potomac Electric Power Company - its Request for Approval of a Revised Project Operational Date for the Fairmount Heights Energy Storage System Project. Case No. 9619 (ML 312837) 10/11/2024
168 Delmarva Power & Light Company - its Request for Approval of a Revised Project Operational Date for the Ocean City Battery Energy Storage System Project. Case No. 9619 (ML 312838) 10/11/2024